View project ↗Arclodge at Powder Mountain

Project facts
- Client
- Powder Haven
- Architect
- Hart Howerton
- Interior designer
- Champalimaud Design
- Structural Engineer of Record
- RJC
- General contractor
- Jacobsen Construction
- Mass timber roof area
- 55,000 sq. ft.
- Location
- Eden, UT, USA
- Status
- In Construction
- Our involvement
- Timber engineering, detailing, fabrication and supply, with site supervision
Photography & imagery
- Diagrams / renders
- Hart Howerton
Overview
Arclodge is a new all-season clubhouse at Powder Mountain, shaped by two sweeping roof forms that echo the arcs skiers trace through fresh snow. Designed by Hart Howerton, the 73,000-square-foot members' lodge brings dining, wellness, recreation and social spaces together at the heart of Powder Haven.
A timber lodge
StructureCraft's timber structure comprises 55,000 sqft across the north and south wings. Douglas-fir glulam columns, beams and purlins support a dowel-laminated timber roof, with hybrid king-post trusses spanning across the larger rooms. 21,000 square feet of interior roof uses acoustic DLT, allowing the exposed deck to act as structure, finished ceiling and acoustic surface.
Negotiating a high mountain site
Fabrication and delivery planning responded directly to the high-mountain site. A 48-foot trailer limit governed member lengths and loading, connections are being preassembled where practical, and the DLT panels are receiving a shop-applied temporary weather membrane. The project is under construction and will open for the 2028 ski season.