StructureCraft Headquarters

Abbotsford, BC, Canada · Completed 2017

StructureCraft Headquarters illuminated at night

Project facts

Owner
StructureCraft
Architect
Keystone
Area
60,000 sf.
Location
Abbotsford, BC, Canada
Status
Completed 2017
Our involvement
Engineer of Record
Engineer-Build

Photography & imagery

Completed photography
Alan Gomez; Calvin Owen Jones
Diagrams / renders
Keystone

A 60,000 sqft facility including a consulting office and manufacturing plant

We lead all consulting and construction operations out of our 60,000sqft facility in Abbotsford, British Columbia, an hour outside of Vancouver. This headquarters, a model of engineering efficiency, sets a new standard in office and industrial building design with wood.

Our 10,000 sqft consulting office, located directly next to our manufacturing/research plant, directs all North American and international projects, both in the consulting phase and throughout construction. The office hosts our Business Development, Engineering & Drafting, Finance, and Project Management departments. Operating in unison with these departments, our 50,000 sqft plant manufactures Dowel Laminated Timber, North America's first all-wood mass timber product, as well as a variety of specialty timber structures. Our site installation teams are directed out of this plant.

The prefabricated wall and roof panels for our plant were designed with a variety of mass timber and engineered wood products, including DLT, LSL, NLT, and Glulam. To demonstrate the flexibility of mass wood in industrial buildings, StructureCraft designed the entire building as a demountable structure, providing flexibility to expand or move the facility entirely to a new location.

We believe there's a more efficient and effective way to construct the industrial buildings of the future using this method.

The new facility was designed to explore what could be possible using wood for a simple industrial building with a tight budget. That exploration, while not simple during the design phase, has created a prototype which proves that modern industrial buildings may be created cost-effectively, and attractively, using wood.

Highlights

  • The erection of the timber superstructure commenced on a Monday, and our crew had the entire building installed by that same Friday.

  • In just one week, all four walls and a 40,000sqft roof were installed.

Updates

In 2022, we expanded our manufacturing & research facility by 10,000 sqft, allowing for more efficient production of DLT and other unique timber products.