Lafayette Library
Architect
Killefer-Flammang Architects
General Contractor
Overaa Construction
Our Service
Engineer of Record (Gerald Epp)
Engineer-Build
Engineer-Build
Area
19,000 sf.
Location
Lafayette, CA, USA
Status
Completed 2009
This 19,000 sq. ft. 3D timber structure is constructed of Parallam space trusses, beams, rafters, struts and turned support columns. All members were pre-fabricated in the shop along with the insulated structural roof panels and the acoustically-insulated, finished ceiling panels. We erected and set the geometry of the main part of the roof by pre-assembling large hybrid wood-steel trusses on the ground, and fitting them rapidly into place.